Community Construction Updates For Citi Bike Stations, Rebuild by Design, Flood Infrastructure and Sewer Upgrades The City of Hoboken is continuing with a number of quality of life projects this…

Community Construction Updates For Citi Bike Stations, Rebuild by Design, Flood Infrastructure and Sewer Upgrades

The City of Hoboken is continuing with a number of quality of life projects this week. Below are construction updates on the installation of Citi Bike stations, Rebuild by Design flood protection project, 5-acre Northwest Resiliency Park, flood infrastructure and sewer upgrades.  Schedules may change pending weather conditions.

To see a map of active road closures in Hoboken, visit https://streets.populus.ai/hoboken/closures

Got photos or video from this event?Share them with your neighbors. Upload to Hudson TV and your name stays on it.
Upload video or photos

Citi Bike Docking Station Installations

During the next several weeks, Lyft will continue to install bike share docking stations as part of the expansion of the Citi Bike program into Hoboken, as announced by Mayor Bhalla and Jersey City Mayor Steve Fulop last week. When complete, the expansion will bring 29 docking stations, capable of parking 300 bikes, to Hoboken. For a map of installation progress visit https://arcg.is/f9nzH.

Residents can also use the Citi Bike or Lyft mobile applications for real-time bicycle and docking space availability. To learn more about the bike share program, please visit http://www.hobokennj.gov/resources/bike-share.

Docking Station Installation Schedule

Thursday, May 20

  • Calle Clinton en la calle 7
  • calle Jackson en la calle 8

Friday, May 21

  • River Terrace en la calle 6
  • La calle 7 en la calle Monroe

Temporary Parking Restrictions for Citi Bike installations

Thursday, May 20 – 7:00am – 4:00pm

  • Calle Clinton, lado oeste, desde la entrada de Acme hasta la intersección con la calle 7
  • calle Jackson, ambos lados, desde la intersección con la calle 8 al norte hasta aproximadamente la mitad de la cuadra
  • 4th Street, ambos lados, de la calle Clinton a la calle Grand

Friday, May 21 – 7:00am – 4:00pm

  • River Terrace, ambos lados, desde la calle 6 al norte hasta el callejón sin salida
  • 7th Street, ambos lados, de la calle Jackson a la calle Monroe

Rebuild by Design Hudson River Project and Sewer System Upgrades
The New Jersey Department of Environmental Protection (DEP) is beginning the construction phase for the Rebuild By Design Hudson River Project – Sewer System Modifications (SSM). The following is an anticipated work schedule for the upcoming two weeks. Schedules may change due to unforeseen weather conditions. Field work will be starting the week of May 17th and will be focused on test pits to identify existing utilities.

The project team will be engaging in the following activities this week:

  • Continúe con las pruebas de abismo para confirmar las ubicaciones de las utilidades existentes en toda la zona de trabajo del sur y comience las operaciones de abismo de pruebas en las ubicações de las fosas de prueba de la zona de empleo del norte.

North Work Area:

  • A lo largo de Hudson Street desde la 14a a la 15a; a lo largo de la 14a calle desde Washington St. hasta Hudson St.

South Work Area:

  • La intersección de Observer Hwy y Hudson St.
  • Este trabajo se llevará a cabo durante el día entre las 8:00 a.m. y las 6:00 p.m.
  • El ensayo se limita a zonas de trabajo compactas y puede implicar reducciones parciales de carril. La policía estará en el lugar para facilitar y dirigir el tráfico según sea necesario.

Project Background:

The Rebuild By Design – Hudson River Project is a comprehensive urban stormwater management program that takes a multi-faceted approach intended to address flooding from both major storm surge and high tide as well as from heavy rainfall events. These events often occur individually, but can also occur together, increasing their impacts. The program includes four components: Resist, Delay, Store and Discharge. This portion of construction addresses the separation of stormwater structures from the combined sewer system outside of the Resist structure.

Construction is planned to begin in May on the South Work Area of the Rebuild By Design Hudson River Project – Sewer System Modifications Project. Construction in the North Work Area is planned to begin in October 2021.  This project will consist of a new storm sewer system, with portions of the existing NHSA combined sewer inlets set to be disconnected and manholes to be sealed and lined. Separation of the stormwater system in the exterior areas will prevent tidal surge backflow into the combined system that could cause flooding on the interior side of the line of protection created by the Resist Structure, once constructed. Stormwater collected in the SSM separated area will gravity flow into the Hudson River.

This United States Department of Housing and Urban Development is funding the project, allocating $230 million to the overall Rebuild By Design Hudson River Project.

HOW TO STAY INFORMED? Sign up to receive Weekly Construction Advisories here.

Live Map of upcoming street closures or partial lane closures here.

QUESTIONS? If you have questions, or would like to learn more about the Sewer Separation Modification Work, please contact your Community Construction Liason (CCL): Erin Percifull | 1-800-252-0219 | rbdhinquiries@portal3.pbid.com

More information about the Rebuild By Design Hudson River Project is available at https://www.nj.gov/dep/floodresilience/rbd-hudsonriver.htm.

Hudson County Road Repaving

Locations: 12th Street between Hudson Street and Sinatra Drive; Sinatra Drive North between 12th Street and Constitution Court

The following construction activities and traffic management are anticipated this week starting on Monday May 17, 2021 to Friday May 21, 2021 between the hours of 8:00am and 6:00pm as part of Hudson County Paving Program.

Work Activities

  • Instalación de pasarela de ADA de hormigón

Traffic Management

  • Se pueden desviar el tráfico para permitir operaciones concretas
  • La policía de Hoboken manejará el flujo de tráfico en las intersecciones para cualquier cierre de carril.
  • No se permitirá estacionar en esta zona durante las horas de trabajo.

5-acre Northwest Resiliency Park

Construction continues on the 5-acre Northwest Resiliency Park, which will be New Jersey’s largest resiliency park. The park will have above and below ground infrastructure to withhold up to 2 million gallons of rainwater to help mitigate local flooding. The contractor will undertake the following activities this week between 8:00am and 4:00pm, subject to weather conditions:

  • Construir dispositivos de gestión de aguas pluviales y barricadas en las calles locales detrás de cercas de construcción.
  • Construye el muro de escalada.
  • Construir fundaciones para edificios y refugios en el campo deportivo multiuso.

The City uses a combination of low interest and interest-free loans, principal forgiveness for the resiliency features, and grant money to save over $19 million over the life of the project. The Northwest Resiliency Park also utilizes the Open Space Trust Fund to pay for the construction costs of the Northwest Park, and is not utilizing any funding from the 2020 municipal budget.

More information about the Northwest Resiliency Park construction is available at www.hobokennj.gov/nwpark

North Hudson Sewerage Authority Projects to Mitigate Flooding Events in Northwest Hoboken, Reduce Combined Sewer Overflows (CSOs)

To reduce Combined Sewer Overflows (CSOs) into the Hudson River and mitigate flooding events in Northwest Hoboken, the North Hudson Sewerage Authority (NHSA), in partnership with the City of Hoboken, is constructing a pumping station and a two-story electrical and mechanical building on the Northwest Resiliency Park (NWRP) site. This, along with associated sewer infrastructure in and around the site, is designed to reduce CSO events in the H6/H7 sewershed in Northwest Hoboken. The project also includes the installation of two advanced hydrodynamic separators, an inlet gravity sewer connection and a portion of a stormwater discharge force main connection to the limits of the resiliency park site.

In addition, NHSA will also build a stormwater collection gravity trunk sewer pipeline and appurtenances along 13th Street from Adams Street to Madison Street, and a stormwater force main sewer pipeline and appurtenances along a portion of 13th street from Jefferson Street to Adams Street. Outside of the Northwest Resiliency Park site, the work will include excavation and demolition of existing pipe and structures; and installation of piles and new sewer pipe and precast structures in the roadway of 13th Street between Adams Street and Madison Street.

The following construction activities and traffic management are anticipated this week between 8:00am and 4:30pm.

Work Activities

  • Continúe excavando fosas de prueba, cortando vías de sierra y colocando asfalto temporal a lo largo de la calle 13 entre Adams Street y Madison Street, en las intersecciones de la calle 13, y Madison Street y en la intersección de Adams Street y la calle 13, para futuros alcantarillados de aguas pluviales y de gravedad.
  • Continúa la instalación de pilas helicoides en la calle 13 entre la calle Madison y la calle Adams, en la calle Madison en la intersección de la calle 13 y en la calle Adams en la intersección con la calle 13.
  • Comienza la excavación de estructuras de alcantarillado en la calle 13 entre la calle Madison y la calle Adams, en la calle Madison en la intersección de la calle 13 y en la calle Adams en la intersección con la calle 13. Este trabajo incluye la instalación preliminar de desagüe de pozo.
  • Continúe la instalación de vigas de acero para la zona de pre-tratamiento y el apoyo de la estación de bombeo para la excavación.
  • Excavación del suelo de la estación de bombeo y extracción para su eliminación.
  • Se prevé que se inicien las obras de instalación de micropillas hacia el final de la semana del 5/17/2021.
  • Muestreo de suelo a lo largo de la calle 13 incluyendo las intersecciones de Madison Street, Jefferson Street y Adams Street.
  • Continúe la construcción de desagüe y operación de las instalaciones de tratamiento ubicadas dentro del estacionamiento en la intersección de la calle 13 y la calle Jefferson.

Traffic Management

  • Cierre periódico de la calle 13 entre la calle Adams y la calle Madison entre las 8:00 a.m. y las 4:30 p.m. La carretera será reabierta por la noche y durante el fin de semana cuando no se produzca ningún trabajo. La intersección de la calle Jefferson y la calle 13 también se incluirá en este cierre.
  • Cierre periódico de la intersección de la calle 13 y la calle Adams durante el día entre las 8:00 am y las 4:30 pm.
  • Cambios periódicos de carril y/o cierres de carril en la calle Madison en la intersección de la calle 13. La policía de Hoboken ayudará con el flujo de tráfico en esta intersección para cualquier cierre de carril.
  • No se permitirá estacionar en esta zona durante el cierre.
  • Aunque no se permitirá el tráfico peatonal durante las horas laborales, el contratista garantizará un tráfico peatonal seguro cuando el trabajo se cierre durante la noche.
Share this with your neighbors
Were you there? Send us your photos and video.Published tips earn 50 points and a credit with your name.
Send a tip

More from Hoboken

All Community
320 × 50

Send Us a News Tip

See something? Send us a photo, video, or tip. You could earn points!

Breaking News Police/Crime ICE/Immigration Accident Fire Sports Community Politics Other
Tap to upload photo or video (max 50MB)
Earn Points! Every tip = 10 pts. Published tip = 50 pts. Refer a friend = 25 pts. Top reporters get featured on our site!