| Updates on Northwest Resiliency Park, Rebuild by Design, Citi Bike installations, and Stevens Park Spray Area Upgrades
The City of Hoboken is continuing with a number of quality of life projects this week. Below are construction updates on the 5-acre Northwest Resiliency Park, flood infrastructure improvements, Rebuild by Design, Citi Bike installations, and Stevens Park spray area upgrades. Schedules may change pending weather conditions. To see a map of active road closures in Hoboken, visit https://streets.populus.ai/hoboken/closures Rebuild by Design Hudson River Project – Sewer System Modification (SSM) The New Jersey Department of Environmental Protection (DEP) is beginning the construction phase for the Rebuild By Design Hudson River Project – Sewer System Modifications (SSM). The following is an anticipated work schedule for the upcoming week. Schedules may change due to unforeseen weather conditions. Field work will be continuing the week of June 21st and will involve saw cutting of the roadway, setting manholes, and installing catch basins and pipe runs for the stormwater management system. The project team will be engaging in the following activities this week:
Construction is planned to begin in May on the South Work Area of the Rebuild By Design Hudson River Project – Sewer System Modifications Project. Construction in the North Work Area is planned to begin in October 2021. This project will consist of a new storm sewer system, with portions of the existing NHSA combined sewer inlets set to be disconnected and manholes to be sealed and lined. Separation of the stormwater system in the exterior areas will prevent tidal surge backflow into the combined system that could cause flooding on the interior side of the line of protection created by the Resist Structure, once constructed. Stormwater collected in the SSM separated area will gravity flow into the Hudson River. This United States Department of Housing and Urban Development is funding the project, allocating $230 million to the overall Rebuild By Design Hudson River Project. HOW TO STAY INFORMED? Sign up to receive Weekly Construction Advisories here. Live Map of upcoming street closures or partial lane closures here. QUESTIONS? If you have questions, or would like to learn more about the Sewer Separation Modification Work, please contact your Community Construction Liason (CCL): Erin Percifull | 1-800-252-0219 | rbdhinquiries@portal3.pbid.com More information about the Rebuild By Design Hudson River Project is available at https://www.nj.gov/dep/floodresilience/rbd-hudsonriver.htm. SUEZ Routine Water Infrastructure Maintenance and Outage Alerts To see if SUEZ is working in your area and if your service may be affected, please enter your address into the SUEZ Water Advisory Map, please check the “Outage & Alerts Map” at: https://www.mysuezwater.com/water-in-my-area/water-alerts-map/New%2520Jersey Northwest Resiliency Park Construction continues on the 5-acre Northwest Resiliency Park, which will be New Jersey’s largest resiliency park. North Hudson Sewerage Authority projects to mitigate flooding events in Northwest Hoboken, reduce Combined Sewer Overflows (CSOs) To reduce Combined Sewer Overflows (CSOs) into the Hudson River and mitigate flooding events in Northwest Hoboken, the North Hudson Sewerage Authority (NHSA), in partnership with the City of Hoboken, is constructing a pumping station and a two-story electrical and mechanical building on the Northwest Resiliency Park (NWRP) site. This, along with associated sewer infrastructure in and around the site, is designed to reduce CSO events in the H6/H7 sewershed in Northwest Hoboken. The project also includes the installation of two advanced hydrodynamic separators, an inlet gravity sewer connection and a portion of a stormwater discharge force main connection to the limits of the resiliency park site. In addition, NHSA will also build a stormwater collection gravity trunk sewer pipeline and appurtenances along 13th Street from Adams Street to Madison Street, and a stormwater force main sewer pipeline and appurtenances along a portion of 13th street from Jefferson Street to Adams Street. Outside of the Northwest Resiliency Park site, the work will include excavation and demolition of existing pipe and structures; and installation of piles and new sewer pipe and precast structures in the roadway of 13th Street between Adams Street and Madison Street. The following construction activities and traffic management are anticipated this week between 8:00am and 4:30pm. Work Activities
Traffic Management
Although 13th Street will be closed for overnight periods, there will be no work performed beyond the normal working hours of 8:00am – 4:30pm.
Southwest Park Expansion (Block 10) The City of Hoboken is constructing the Pop-up Park at Block 10. The City and its contractors will undertake the following activities this week between 8:00am and 4:00pm, subject to weather conditions: installation of playground safety surface, pruning hedges, and striping courts. More information about the Southwest Park Expansion and Pop-up Park is available at https://www.hobokennj.gov/resources/southwest-park Stevens Park Spray Area The City of Hoboken is improving the spray area at Stevens Park. Upgrades will include the installation of new splash pad features, underground drainage system, and refurbishing/relocating the concrete sculptures from the splash pad to a location nearby in Stevens Park. The spray area will remain closed through Friday July 2, 2021. Citi Bike Expansion As of June 25, 22 Citi Bike docking stations have been installed and are active in Hoboken. You can check the citywide installation progress here. A docking station on Willow Avenue at 12th Street will be installed on Friday, July 2. To facilitate the installation of the docking station, on July 2, between 7:00am and 4:00pm, parking will be prohibited on the west side of Willow Avenue between 12th Street and the NJ Transit bus stop just south of the intersection with 13th Street. The protection of each construction site, workers, and the general public are of the utmost priority. Contractors, construction managers, subcontractors, and suppliers are following CDC guidelines and employer policies for COVID-19 protection. |